County of St. Paul No 19

Public Works Meeting

AGENDA

Meeting #:
Date:
Time:
-
Location:
Board Room

  • Richland road.  Road tech (Rework complete)
  • Garner Road (TWP RD 610) (Complete)
  • Lafond Waste water road (RGE RD 564) (Complete)
  • Capp Road (TWP 590 RGE111) (Road grade complete, placing soils)
  • BF72562 (SE 14-62-11-W4) (Complete)
  • Marcoux (RGE RD 85 North of Armistice RD (Complete)
  • Dargis (Rge Rd 91 north of Hwy 28) (Under construction)
  • Boscombe (Rge Rd 103 south of Hwy 28) (2019)
  • Ashmont landfill Cell (Complete)
  • Looy (Twp Rd 582 East of Hwy 36) (Late October)
  • Berlingette (Rge Rd 103 south of Twp Rd 590) (2019)
  • Hook Lake (Rge Rd 74 south of Armistice Rd) (Late October)
  • Laurier Lake Slide (2019)
  • Moosehills Road and RGE RD 62 South of Moose hills  (under construction Nov 5th)
  • Batty lake pit. Partial Reclamation and exposure of pit run.
  • Miller pit. Partial Reclamation to provide grazing for land owner (Complete)
  • Planning for winter projects such as RGE RD 110 North of 646, TWP RD 580 West of RGE RD 101 1/2mile, RGE RD 92 North 590,
  • Approach construction
  • 2019 plans for construction
  • Repairing culverts/drainage issues. Started inspection and prep of culverts to prep for spring run-off.
  • Gravel haul to roads to continue till freeze up
  • Line painting on paved roads (Completed 42km)
  • Pavement repairs finished in Parkland, Ashmont and Mallaig HWY, working in Floatingstone.
  • Mulching Elk Point Airport
  • Preparing for winter snow removal and how we respond
  • On call phone
  • Complaint tracking system - See attached
  • Now in Division 3, Lac Bellevue and St. Edouard  - Shutting down Oct 26th
  • See attached oil proposals and estimate 2018
  • Ripping and Packing in Division 3
  • Cork Hall parking lot cold mix complete

Report on dust controls done with MG30 to be presented on Tuesday, as per discussions at September 25 Public Works Meeting.

  • Crusher temporarily shut down due to illness and lack of staff.  Start up later this week. Crushing crew working on construction and maintenance for a week.
  • Currently at Peter Danyluk’s to crush 20,000.
  • Crusher has produced 142,000 Yards of usable gravel this season
  • Gravel swap from CN to JMB (Frog Lake) to allow cure time on Richland road
  • Crusher Cone update on current cost - as per request at Strategic Planning
  • Well in Lower Mann abandon and cement pad removed top soil placed.
  • Clay hauled to McRae hall.
  • Ashmont to Mallaig water line update
  • Desludging Mallaig lagoon cancelled until next year
  • Bobcat mini track hoe is now in our yard.
  • T40 (2006 Kenworth T800) Plate Truck in summer Sander and Plow Truck in winter - to be sold in November. It is set up as a sander and will be going to sale week of Oct 22
  • We have received the new plow trucks T-104 and T-105 one is currently pulling water trailer while the other is set up as a sander.
  • We have four plow trucks set up for sanding as well as we are starting on the graders.
  • MS-04 Buggy transmission is still in rebuild shop and will probably not be ready for work this fall but will have a one year warranty on it. This will cover it for next summers use.
  • MG 01 repairs to final drive $10,000 no warranty,
  • Maintenance work and general repairs are on going and the shop is constantly going.

Reconstruction of TWP Rd 560 East of Hwy 897 as discussed with CNRL to start next week.  

Overview on:

- First Nation Consultation

  • Golden Gate Pit

- Water Act

  • For winter projects - TFA

- SME / SML

       Application for SML Golden gate

- Bird Survey - Migratory bird season over starting again March 15th 2019

The 11th Annual Fall Classic Farmer's Spiel will be held November 1 to 3, 2018 in Mallaig.  They are requesting cash to help cover expenses or items to be used as prizes.  Registration for the spiel is $160.

Attached is a letter from Kim Farrell, owner of Lot 17, Block 1, Plan 7620518, in response to the County's letters from May 14th and August 20.

 

On May 14th, she received a letter from the County advising that she needed a permit for her bunkhouse, based on information provided to Planning and Development by the County Assessors.  She applied for the permit but Planning and Development has not processed the permit.  

 

The Assessors also notified the taxation department that the structures were on reserve land.  The County's Surveyors confirmed the location of the structures on the reserve land.  Administration then issued a letter directing her to remove the cabin, 2 sheds and hot tub from Lot 43R, Block 1, Plan 7620518.  

 

Mrs. Farrell has contacted Councillor Hedrick and is requesting that her buildings be permitted to say on the environmental reserve.  

Attached is a letter from Bill Simon, owner of Lot 28, Block 1, Plan 7620518, in response to the County's letter of August 20th directing that he remove the boathouse and eavestrough on the shed which are encroaching on Lot 43R, Block 1, Plan 7620518.  

 

Mr. Simon has contacted Councillor Hedrick and is requesting that the County:

  • Grandfather the buildings in
  • Issue an Encroachment Agreement
  • Survey the portions out and add them to the existing properties

Further to the October 18th Strategic Planning discussions, Public Works will present Council with their five-year capital plan in order to finalize the Strategic Plan for approval at the November Council Meeting.  

Council was provided with a summary of information generated from the meetings with Octopus Creative.  We would be looking for a motion to approve the statements Council prefers for the Visions, Missions and Values.

Meeting scheduled for November 20th from 9:00 - 9:25 a.m. during RMA Convention. 

Need to confirm topics for discussion.  So far we have - 

  • STIP
  • mowing/weed control along provincial highways

Looking for feedback on the application form. 

11.15

11.16

11.17