  • Miller road - Complete other than top soils and back sloping
  • Owlseye and 103 North - Under construction
  • Northern Valley Rd - Complete
  • Moose hills slide - STIP grant application.
  • Vincent Lake BF - finished
  • Richland BF - Under Construction C
  • Camp Lake Rd. Challenges?
  • Lafond Waste water Rd -TWP Rd 564 Postponed to 2018
  • Iron Horse Trail - Heinsburg meeting
  • Stoney Lake Parking Lot - Winter 2018
  • Seed Cleaning Plant - Change of timing
  • Elk Point Ag Society - Drainage complete
  • Ashmont Transfer Station Cell - Planned for early winter
  • Done for the season
  • Update on total dust controls
  • Currently crushing Gravel at CN pit. Approx 40,000 yards crushed.
  • Gravel testing - Agreements secured and plan to start exploring after freeze up.
  • Conversation started with Carillion about selling sand to them in 2018
  • From Owlseye north on RGE RD 103 and East on TWP Rd 591 and 592 and Horseshoe Bay area
  • Will continue throughout County until snow load is too heavy then move to Iron Horse Trail.
  • Lac Bellevue - Application sent in
  • Laurier Lake - Pads ordered
  • Ashmont Seniors home - Met to discuss better options for sidewalk
  • Mallaig sidewalk - Repaired
  • Cross walk painting - Completed
  • Line Painting - Murphy, Moose Hills, Krider, and Lindberg - 45 km done
  • Mallaig gravel storage area permanently prepped for storage.  Chain link fence to go up along road.

Lafond Waste Transfer - Complete

  • Trucks converting over for sand and snow plowing
  • Graders tires and wings changeover for winter 

October 27 - Seasonal truck drivers and some labourers will be finished for the year.  Seasonal construction crew, crusher crew and some labour staff will stay on until mid November.  

Public Works tendered the construction of 1 mile along Township Road 564, Lafond Sewage Road.  The first time the project was advertised, the tenders were received based on the contractors supplying gravel, so the tenders were not accepted and the project was re-tendered.  Again, the bids came in higher than expected so the tender was not awarded.  The advertisement for the road construction project clearly stated "highest tender not necessarily accepted".

 

FCM Contracting Ltd from Grande Prairie submitted a tender each time.  They are now requesting compensation for their efforts and waste of time in the amount of $500, which they believe is 1/3 of what they spent on office supplies, vehicle mileage and fuel, accommodation and meals. 

 

Administration is recommending to deny the request from FCM Contracting Ltd. for compensation.

The St. Paul Elks is requesting a donation for their radio auction which will be held on Sunday, November 5th.  They are requesting a donation to be used as an auction item.  In the past, Council approved two ten cubic yard loads of gravel, to be delivered as per policy PW-59.

 

Administration is recommending to approve two ten-cubic yard loads of gravel.